Federal Grid Company develops measures that would make any identified risk consistent with the “preferred
risk,” i.e. the maximum permissible risk which the Company seeks or is ready to maintain. The response depends
on risk relevance, impact on the likelihood and effect of a given risk, costs of risk materialisation, and risk
benefits. After deciding on response measures, the Company’s executives assess the residual risk that must not
go beyond the “preferred risk” level.
See details about the risk management system in Federal Grid Company in section GOVERNANCE AND
DEVELOPMENT / Risk Management
Industry Risks
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Department of Economic Planning
and Tariff Setting
2014

2015
 |
- The amount of investable funds
in the tariff was reduced relative
to the tariff sources of funds
for the Company’s Investment
Programme that has been taken
into account when tariffs for
electricity transmission were
approved. The reduction was
caused by an increased cost of
debt
- Actual revenues from electricity
transmission services were
lower due to a changed order
of payment for services; this
change had not been taken into
account when tariffs were set
- The costs of electricity
transmission services via foreign
energy systems increased due
to changes of foreign currency
rates
- tariff on
electricity transmission deviated
from the one that was included in
the business plan
|
- The amount of investable funds in the tariff was
reduced relative to the tariff sources of funds for
the Company’s Investment Programme that has
been taken into account when tariffs for electricity
transmission were approved. The reduction was
caused by an increased cost of debt
- Actual revenues from electricity transmission
services were lower due to a changed order of
payment for services; this change had not been
taken into account when tariffs were set
- The costs of electricity transmission services via
foreign energy systems increased due to changes
of foreign currency rate
|
- Draft proposed changes to the corporate Investment Programme and the
structure of sources of financing and changes in the structure of tariff decision
in terms of tariff sources of financing for the corporate Investment Programme.
- Draft and submit proposed amendments to laws and regulations on tariff setting
and on defining the declared capacity that is used in setting the tariffs, as well
as the volumes of electricity transmission to customers, and other changes.
- Draft proposals to include lost revenues (caused by a reduced volume of
services and increased costs of electricity transmission services via foreign
energy systems) in the gross revenues. These proposals will be submitted to the
Federal Tariff Service.
- Implement actions targeted at improving the efficiency of the Company’s
operations and investments, consistent implementation of the approved
parameters of RAB regulation and at drawing up well-balanced and economically
justified proposals about how to adjust and set these parameters.
- Improve the quality of budget planning and develop a system of budget
control through improving the corporate Budget Code and integrating the risk
management processes in the system of medium-term and long-term business
planning.
|
- The cost of debt increased because
interest payments increased by RUB
7,091 million (or 30.2%) due to an
increase of the consumer price index
- Payments for services of other (foreign)
distribution grid companies increased by
RUB642 million (or 30.6%)
- According to an approved tariff &
balance profile, payments should be
made for the declared capacity. In
practice, direct customers pay for actual
capacity which means that the required
gross revenues declined by RUB484
million (or 0.3%)
|
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Department of Economic Planning
and Tariff Setting
2014

2015
 |
- The amount of investable funds
in the tariff was reduced relative
to the tariff sources of funds
for the Company’s Investment
Programme that has been taken
into account when tariffs for
electricity transmission were
approved. The reduction was
caused by an increased cost of
debt
- Actual revenues from electricity
transmission services were
lower due to a changed order
of payment for services; this
change had not been taken into
account when tariffs were set
- The costs of electricity
transmission services via foreign
energy systems increased due
to changes of foreign currency
rates
- tariff on
electricity transmission deviated
from the one that was included in
the business plan
|
- The amount of investable funds in the tariff was
reduced relative to the tariff sources of funds for
the Company’s Investment Programme that has
been taken into account when tariffs for electricity
transmission were approved. The reduction was
caused by an increased cost of debt
- Actual revenues from electricity transmission
services were lower due to a changed order of
payment for services; this change had not been
taken into account when tariffs were set
- The costs of electricity transmission services via
foreign energy systems increased due to changes
of foreign currency rate
|
- Draft proposed changes to the corporate Investment Programme and the
structure of sources of financing and changes in the structure of tariff decision
in terms of tariff sources of financing for the corporate Investment Programme.
- Draft and submit proposed amendments to laws and regulations on tariff setting
and on defining the declared capacity that is used in setting the tariffs, as well
as the volumes of electricity transmission to customers, and other changes.
- Draft proposals to include lost revenues (caused by a reduced volume of
services and increased costs of electricity transmission services via foreign
energy systems) in the gross revenues. These proposals will be submitted to the
Federal Tariff Service.
- Implement actions targeted at improving the efficiency of the Company’s
operations and investments, consistent implementation of the approved
parameters of RAB regulation and at drawing up well-balanced and economically
justified proposals about how to adjust and set these parameters.
- Improve the quality of budget planning and develop a system of budget
control through improving the corporate Budget Code and integrating the risk
management processes in the system of medium-term and long-term business
planning.
|
- The cost of debt increased because
interest payments increased by RUB
7,091 million (or 30.2%) due to an
increase of the consumer price index
- Payments for services of other (foreign)
distribution grid companies increased by
RUB642 million (or 30.6%)
- According to an approved tariff &
balance profile, payments should be
made for the declared capacity. In
practice, direct customers pay for actual
capacity which means that the required
gross revenues declined by RUB484
million (or 0.3%)
|
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Technological Development
Department
2014

2015
 |
Risks related to the untimely
meeting of contractual obligations
under contracts for technological
connection, including deviation
of the actual quality level of
the technological connection
services from the level established
during tariff regulation. The
quality level is measured as per
Section 3 of Executive Order
No. 718 dated 14 October 2013,
issued by the Ministry of Energy,
as the aggregate impact by the
quality parameters of reviewing
applications for technological
connection; execution of contract
for technological connection,
compliance with the antimonopoly
legislation and the quality of
customer services. |
|
The Company approved the Programme for Improving the Efficiency of
Technological Connection to Electric Grids of Federal Grid Company and Increasing
Transformer Capacity Utilisation. It includes actions targeted at initiation of
amendments to the Russian laws (law-making) and organisational actions.
Institutional actions of the Programme are targeted at improving the efficiency
of Federal Grid Company’s operations when the Company provides technological
connection services if tariff sources of financing are insufficient, including:
- Drafting and implementation of template documents in order to unify the
document flow in the process of technological connection of customers
- Actions to increase capacity utilisation by identifying and decommissioning
inefficient capacities
- Setting of schedules for completion of procedures by the Company’s structural
units and implementation of actions to improve control over scheduled
deadlines at all stages of business process, from registration of an application
for technological connection to full performance of contractual obligations
Law-making activities in the context of these risks include the drafting of
proposed amendments to laws and regulations that govern relations of the parties
in the process of technological connection (including those that regulate the
fundamentals of pricing when individual tariffs for technological connection are
set) and responsibility of grid organisations and counterparties for complying
with the material terms and conditions of contracts for technological connection.
These proposals were communicated to the regulators (the Federal Anti-Monopoly
Service and Ministry of Energy).
Federal Grid Company monitors and updates information about transformer
capacity which is free for technological connection of customers and generation
facilities. This monitoring is done across all feeding centres, and information is
available at the corporate website. |
|
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Technological Development
Department
2014

2015
 |
Risks related to the untimely
meeting of contractual obligations
under contracts for technological
connection, including deviation
of the actual quality level of
the technological connection
services from the level established
during tariff regulation. The
quality level is measured as per
Section 3 of Executive Order
No. 718 dated 14 October 2013,
issued by the Ministry of Energy,
as the aggregate impact by the
quality parameters of reviewing
applications for technological
connection; execution of contract
for technological connection,
compliance with the antimonopoly
legislation and the quality of
customer services. |
|
The Company approved the Programme for Improving the Efficiency of
Technological Connection to Electric Grids of Federal Grid Company and Increasing
Transformer Capacity Utilisation. It includes actions targeted at initiation of
amendments to the Russian laws (law-making) and organisational actions.
Institutional actions of the Programme are targeted at improving the efficiency
of Federal Grid Company’s operations when the Company provides technological
connection services if tariff sources of financing are insufficient, including:
- Drafting and implementation of template documents in order to unify the
document flow in the process of technological connection of customers
- Actions to increase capacity utilisation by identifying and decommissioning
inefficient capacities
- Setting of schedules for completion of procedures by the Company’s structural
units and implementation of actions to improve control over scheduled
deadlines at all stages of business process, from registration of an application
for technological connection to full performance of contractual obligations
Law-making activities in the context of these risks include the drafting of
proposed amendments to laws and regulations that govern relations of the parties
in the process of technological connection (including those that regulate the
fundamentals of pricing when individual tariffs for technological connection are
set) and responsibility of grid organisations and counterparties for complying
with the material terms and conditions of contracts for technological connection.
These proposals were communicated to the regulators (the Federal Anti-Monopoly
Service and Ministry of Energy).
Federal Grid Company monitors and updates information about transformer
capacity which is free for technological connection of customers and generation
facilities. This monitoring is done across all feeding centres, and information is
available at the corporate website. |
|
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Environmental Policy Department
2014

2015
 |
Risks related to noncompliance
with the Russian laws on
environmental protection. |
In accordance with a decision taken by the Board
of Directors (Minutes No. 166 dated 3 July 2012),
since 2011 the Company gradually introduced and
certified an environmental management system in
its branches.
In 2015, the environmental management system was
put in place and certified in the branches of MES
Siberia, Western Siberia, Ural and Volga. Besides,
we obtained a unified company-wide certificate for
Federal Grid Company. |
As per Executive Order No. 362 dated 11 September 2015, the Company drew
up a Procedure of Working with Trichlorodiphenyl-Containing Equipment.
Trichlorodiphenyl-containing equipment (total weight: 262.04 tons) was handed
over for salvage / placement from several PMES. |
|
2014

2015
 |
Risks related to the failure
to implement assignment of
the President of the Russian
Federation, dated 6 June 2010
(subclause “l” of Clause 1 in the
List of Assignments No. Pr-1640
and Directive No. 1710p-P13 of
the Government of the Russian
Federation, dated 30 April 2012 “On
the need to ensure that joint-stock
companies with government capital
take a decision on implementation
of voluntary mechanisms of
environmental responsibility”
(hereinafter “Assignments” and
“Directives”) and decisions taken
by the Company’s Board about
the procedure of implementation
and obtaining the certificates for
compliance with the international
standard ISO 14001:2004 for
the Company’s environmental
management system (Minutes
No. 230 of the Board meeting,
dated 3 October 2014). |
|
The Company implements its environmental-saving initiatives in accordance
with the Policy of Innovative Development, Energy Saving and Improvement of
Energy Efficiency adopted by PJSC Rosseti (Minutes No. 222 of the Board meeting
dated 30 June 2014) and Environmental Policy of Federal Grid Company (Minutes
No. 230 of the Board meeting dated 03.10.2014). The Company implements the
decision of its Board of Directors to put in place the system of environmental
management as a voluntary mechanism of environmental responsibility, and obtain
a certificate of compliance with the international standard ISO 14001:2004. The
Company completed a set of actions that would help to embrace all its branches
in one environmental protection framework in accordance with the international
standards. An independent audit of the Company’s environmental management
system was completed. |
|
2014

2015
 |
Reputation risks |
|
The Company follows clearly formulated principles of corporate social
responsibility, given its impact on the national economy, environment and the
society. Particular attention is paid to implementation of charitable, social and
environmental programmes most of which are long-term ones. |
|
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Environmental Policy Department
2014

2015
 |
Risks related to noncompliance
with the Russian laws on
environmental protection. |
In accordance with a decision taken by the Board
of Directors (Minutes No. 166 dated 3 July 2012),
since 2011 the Company gradually introduced and
certified an environmental management system in
its branches.
In 2015, the environmental management system was
put in place and certified in the branches of MES
Siberia, Western Siberia, Ural and Volga. Besides,
we obtained a unified company-wide certificate for
Federal Grid Company. |
As per Executive Order No. 362 dated 11 September 2015, the Company drew
up a Procedure of Working with Trichlorodiphenyl-Containing Equipment.
Trichlorodiphenyl-containing equipment (total weight: 262.04 tons) was handed
over for salvage / placement from several PMES. |
|
2014

2015
 |
Risks related to the failure
to implement assignment of
the President of the Russian
Federation, dated 6 June 2010
(subclause “l” of Clause 1 in the
List of Assignments No. Pr-1640
and Directive No. 1710p-P13 of
the Government of the Russian
Federation, dated 30 April 2012 “On
the need to ensure that joint-stock
companies with government capital
take a decision on implementation
of voluntary mechanisms of
environmental responsibility”
(hereinafter “Assignments” and
“Directives”) and decisions taken
by the Company’s Board about
the procedure of implementation
and obtaining the certificates for
compliance with the international
standard ISO 14001:2004 for
the Company’s environmental
management system (Minutes
No. 230 of the Board meeting,
dated 3 October 2014). |
|
The Company implements its environmental-saving initiatives in accordance
with the Policy of Innovative Development, Energy Saving and Improvement of
Energy Efficiency adopted by PJSC Rosseti (Minutes No. 222 of the Board meeting
dated 30 June 2014) and Environmental Policy of Federal Grid Company (Minutes
No. 230 of the Board meeting dated 03.10.2014). The Company implements the
decision of its Board of Directors to put in place the system of environmental
management as a voluntary mechanism of environmental responsibility, and obtain
a certificate of compliance with the international standard ISO 14001:2004. The
Company completed a set of actions that would help to embrace all its branches
in one environmental protection framework in accordance with the international
standards. An independent audit of the Company’s environmental management
system was completed. |
|
2014

2015
 |
Reputation risks |
|
The Company follows clearly formulated principles of corporate social
responsibility, given its impact on the national economy, environment and the
society. Particular attention is paid to implementation of charitable, social and
environmental programmes most of which are long-term ones. |
|
Country and regional risks
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Strategic Development
Department
Political factors
2014

2015
Economic factors
2014

2015
 |
Political risk factors in 2015 were
minor for the Company because
political stability was maintained.
The most significant economic
risk factors were related to the
deterioration of macroeconomic
fundamentals (GDP, inflation,
unemployment and others). |
Lower oil prices, depreciation of the Ruble exchange
rates to the main foreign currencies and economic
sanctions against the Russian Federation resulted in
the higher relevance of the overall economic risk. |
Risks related to the political and economic situation in the country fall in the group
of risks that the Company cannot manage or influence. |
Market situation deteriorated due to other
factors; electricity consumption declined,
followed by the lower demand for the
Company’s services. |
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Strategic Development
Department
2014

2015
 |
Federal Grid Company manages a
unified national electricity grid on
the larger territory of the Russian
Federation. It has a distributed
network of structural units, and
its assets are located on the
whole territory of the Russian
Federation. Therefore, risk factors
for the Company are weather,
climatic, seismic and other nature
conditions. |
The Company takes these factors into account
when it plans and constructs grid facilities, takes
decisions about protection tools, location of repair
facilities, distance of facilities from the repairs units,
and possible impact of natural phenomena on these
facilities. |
Federal Grid Company operates in compliance with the Unified Technical Policy
of the Electric Grid Complex that was approved by the Board of Directors of
JSC Rosseti (Minutes No. 138 dated 23 October 2013). The aim of the Unified
Technical Policy is to identify the key technical areas that enhance the electric
grid complex’s reliability and efficiency in the short and medium terms with an
appropriate industrial and environmental safety based on innovative principles that
provide non-discriminatory access to electric grids for all market participants. This
includes:
- An increased number of off-road vehicles and use of air drones in the process of
operating the overhead lines and arranging post-accident inspections
- Higher readiness for repair and recovery works
|
Equipment outages and technological
disruptions caused by weather, climatic,
seismic and other nature conditions did
not exceed the estimated levels. |
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Strategic Development
Department
2014

2015
 |
Federal Grid Company manages a
unified national electricity grid on
the larger territory of the Russian
Federation. It has a distributed
network of structural units, and
its assets are located on the
whole territory of the Russian
Federation. Therefore, risk factors
for the Company are weather,
climatic, seismic and other nature
conditions. |
The Company takes these factors into account
when it plans and constructs grid facilities, takes
decisions about protection tools, location of repair
facilities, distance of facilities from the repairs units,
and possible impact of natural phenomena on these
facilities. |
Federal Grid Company operates in compliance with the Unified Technical Policy
of the Electric Grid Complex that was approved by the Board of Directors of
JSC Rosseti (Minutes No. 138 dated 23 October 2013). The aim of the Unified
Technical Policy is to identify the key technical areas that enhance the electric
grid complex’s reliability and efficiency in the short and medium terms with an
appropriate industrial and environmental safety based on innovative principles that
provide non-discriminatory access to electric grids for all market participants. This
includes:
- An increased number of off-road vehicles and use of air drones in the process of
operating the overhead lines and arranging post-accident inspections
- Higher readiness for repair and recovery works
|
Equipment outages and technological
disruptions caused by weather, climatic,
seismic and other nature conditions did
not exceed the estimated levels. |
Financial risk
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Treasury and Corporate Finance
Department
2014

2015
 |
This risk is related to possible
losses and/or the Company’s
inability to meet its obligations in
full due to the following factors:
- CBR’s monetary policy
- Exchange rate fluctuations
- Changes of interest rates
- Inflationary pressures
- The Company’s restricted access
to equity or debt financing
|
|
The Company is implementing an Action Programme (“road map”) to ensure
financial sustainability and enhanced economic efficiency of Federal Grid
Company in 2014–2015, including a package of anti-crisis actions approved by the
Management Board (Minutes No. 1263 dated 10 October 2014). The goals of this
Programme are to achieve the best balance between objectives of the Company’s
investment growth, the level of its shareholder value and profitability; ensure
financial sustainability; and conduct efficient and high-performance business
operations.
The Company developed and implemented actions that are included in the
programmes and have an impact on the outcomes of the Company’s operations.
These include:
- Investment Efficiency Programme which envisages a reduction of investment
costs
- Programme for Substitution of Imported Equipment, Technologies, Materials and
Systems for 2015–2019.
- Maintenance and Repair Costs Efficiency Programme
- Payroll Efficiency Programme
- Programme for Improving Efficiency of Technological Connection to Federal
Grid’s Electric Grids and Increasing Utilisation Ratio of Transformer Capacities.
The Company also implements other actions to minimise the financial effect of the
abovementioned factors:
- It continuously monitors and manages risks related to changes of the regulatory
framework (this is done by departments of finance and economy);
- It takes actions to improve management of the Company’s working capital
and ensure profit from cash flow, including via stronger financial discipline
of counterparties. The Company also implements its policy which envisions
gradual reduction of advances paid to contractors;
- Federal Grid Company handles claims and bad debt recovery, and manages
accounts receivable in order to reduce overdue accounts receivable or prevent
their accumulation by counterparties;
- The Company drafts proposals for the federal executive authorities on how to
change the process of calculation of fines for untimely fulfilment of contractual
obligations;
- The Company conducts negotiations with entities that provide cross-border
electricity transmission services (Kazakhstan, Belarus, the Baltic countries). The
aim of these negotiations is to achieve an agreement not to increase the cost of
transit due to exchange rate changes and synchronise the parameters of tariff
indexation between the countries;
- The Board of Directors established a foreign currency limit on FX transactions in
order to control operations in foreign currency;
- The Company takes actions to obtain various forms of government support
(allocations from the National Wealth Fund, budget allocations via federal
targeted programmes, loans and guarantees via investment projects support
programmes implemented on the basis of project financing and others).
|
The risk materialised in terms of higher
interest rates that affected the average cost
of debt for the Company |
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Treasury and Corporate Finance
Department
2014

2015
 |
This risk is related to possible
losses and/or the Company’s
inability to meet its obligations in
full due to the following factors:
- CBR’s monetary policy
- Exchange rate fluctuations
- Changes of interest rates
- Inflationary pressures
- The Company’s restricted access
to equity or debt financing
|
|
The Company is implementing an Action Programme (“road map”) to ensure
financial sustainability and enhanced economic efficiency of Federal Grid
Company in 2014–2015, including a package of anti-crisis actions approved by the
Management Board (Minutes No. 1263 dated 10 October 2014). The goals of this
Programme are to achieve the best balance between objectives of the Company’s
investment growth, the level of its shareholder value and profitability; ensure
financial sustainability; and conduct efficient and high-performance business
operations.
The Company developed and implemented actions that are included in the
programmes and have an impact on the outcomes of the Company’s operations.
These include:
- Investment Efficiency Programme which envisages a reduction of investment
costs
- Programme for Substitution of Imported Equipment, Technologies, Materials and
Systems for 2015–2019.
- Maintenance and Repair Costs Efficiency Programme
- Payroll Efficiency Programme
- Programme for Improving Efficiency of Technological Connection to Federal
Grid’s Electric Grids and Increasing Utilisation Ratio of Transformer Capacities.
The Company also implements other actions to minimise the financial effect of the
abovementioned factors:
- It continuously monitors and manages risks related to changes of the regulatory
framework (this is done by departments of finance and economy);
- It takes actions to improve management of the Company’s working capital
and ensure profit from cash flow, including via stronger financial discipline
of counterparties. The Company also implements its policy which envisions
gradual reduction of advances paid to contractors;
- Federal Grid Company handles claims and bad debt recovery, and manages
accounts receivable in order to reduce overdue accounts receivable or prevent
their accumulation by counterparties;
- The Company drafts proposals for the federal executive authorities on how to
change the process of calculation of fines for untimely fulfilment of contractual
obligations;
- The Company conducts negotiations with entities that provide cross-border
electricity transmission services (Kazakhstan, Belarus, the Baltic countries). The
aim of these negotiations is to achieve an agreement not to increase the cost of
transit due to exchange rate changes and synchronise the parameters of tariff
indexation between the countries;
- The Board of Directors established a foreign currency limit on FX transactions in
order to control operations in foreign currency;
- The Company takes actions to obtain various forms of government support
(allocations from the National Wealth Fund, budget allocations via federal
targeted programmes, loans and guarantees via investment projects support
programmes implemented on the basis of project financing and others).
|
The risk materialised in terms of higher
interest rates that affected the average cost
of debt for the Company |
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Rules and Regulations Directorate,
Legal Department
2014

2015
 |
These are risks related to changes
in legislation and to regulation of
Federal Grid’s operational areas,
including but not limited to:
- Relations
with other owners of
UNEG facilities;
- Calculation of the justified
value of maximum capacity for
technological connection of
applicants;
- The procedure for defining the
declared capacity to be used
for setting of the electricity
transmission tariffs and
calculation of service costs;
- Technological connection to
the Company’s facilities having
voltage below 110 kW;
- Coordination of electricity market
participants’ programmes for
development of the electric
power industry in the longer
term;
- Customers’ liability for the
untimely payment for services;
- Relations
with the third parties
in technological connection.
|
The factor that affected the changed assessment
of the risk related to the liability of customers for
the untimely payment for services was the passage
of Federal Law No. 307-FZ dated 3 November
2015 “On Amending Several Laws of the Russian
Federation in the Context of Strengthening of
Payment Discipline of Users of Energy Resources.” |
The Company continuously contributes to the drafting of rules and regulations at
the federal level, takes part in the work of inter-ministry panels on the regulation of
the electric power industry, and co-operates with the relevant committees of the
Federal Assembly of the Russian Federation. The following actions were taken in
the reporting year as part of this work:
- Federal
Grid Company drafted proposed amendments to the Federal Law
“On Electric Power Industry” (about relations with other owners of UNEG) and
submitted them to the Russian Ministry of Energy.
- Federal
Grid Company drafted proposed amendments to the rules and
regulations on the establishment of a procedure for the calculation of declared
capacity including for regional grid organisations that purchase services from
Federal Grid Company
- Federal
Grid Company and the Ministry of Energy drafted and promoted
proposed amendments to laws and regulations. These amendments will provide
for exceptional cases of technological connection of the customers’ power
receivers to electric grid facilities having voltage below 110 kV
- Federal
Grid Company drafted proposed amendments to laws and regulations
and submitted them to the Ministry of Energy. The proposals pertain to the
procedure whereby a grid organisation settles relations with the third parties in
technological connection.
- Federal
Grid Company co-operated with the Ministry of Energy, Federal Anti-
Monopoly Service and the State Duma Committee for Energy in order to include
the Company’s proposals in the bill No. 348213-6 “On Amending Several Laws of
the Russian Federation in the Context of Strengthening of Payment Discipline of
Users of Energy Resources.”
|
|
2014

2015
 |
Risks related to public law and
pertaining to:
- Changes of court practices on
issues related to the Company’s
operations
- Balance of interests with other
entities operating in the electric
power industry
|
|
The Company monitors the key trends in court practices pertaining to its main
operational areas. In the reporting period, there were no changes in the court
practices on issues related to Federal Grid Company’s core business that could
have a significant adverse effect on its performance and on the outcomes of court
trials in which the Company is a party. |
|
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
External Communications and GR
Department
2014
2015
 |
Risk related to lower efficiency in
communication with stakeholders
and lower level of the Company’s
transparency.
Information effect if other risks
materialise. |
|
The Company’s information policy is targeted at the efficient disclosure of
mandatory and additional information that helps to raise information openness
and transparency of relations between the Company and its shareholders,
creditors, prospective investors, professional participants of the securities market,
government bodies, the media and other stakeholders. The Board of Directors
(Minutes No, 280 dated 24 August 2015) approved a new version of the corporate
Information Policy which takes into account the requirements of the Russian
Corporate Governance Code.
The Company’s internal rules and regulations on information exchange help to
mitigate the cost of these risks if they materialise. |
|
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
External Communications and GR
Department
2014
2015
 |
Risk related to lower efficiency in
communication with stakeholders
and lower level of the Company’s
transparency.
Information effect if other risks
materialise. |
|
The Company’s information policy is targeted at the efficient disclosure of
mandatory and additional information that helps to raise information openness
and transparency of relations between the Company and its shareholders,
creditors, prospective investors, professional participants of the securities market,
government bodies, the media and other stakeholders. The Board of Directors
(Minutes No, 280 dated 24 August 2015) approved a new version of the corporate
Information Policy which takes into account the requirements of the Russian
Corporate Governance Code.
The Company’s internal rules and regulations on information exchange help to
mitigate the cost of these risks if they materialise. |
|
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Department for the Development
of Technologies for the
Manufacturing of Electrical
Equipment
2014
2015
 |
- Limited or impossible
procurement of electrical
products (caused by legislative
restrictions or ban on import
to Russia either by foreign
countries or by the Russian
Federation); refusal of foreign
producers to co-operate with
the Russian companies;
domestic producers do not
have the required technology,
equipment and competencies
for manufacturing electrical
products that would meet the
present-day requirements)
- Increased prices on electrical
products due to adverse external
factors (Ruble depreciation
against the main currencies;
foreign producers’ discriminatory
policy toward Russian
customers; absence of Russian
analogues of foreign equipment;
or strong dependence of their
manufacturing processes on
imported equipment, inputs and
spare parts)
|
Execution risks related to the Import Substitution
Programme became more relevant in 2015
because external environment further deteriorated,
additional sanctions were imposed on the Russian
Federation by some countries, and Russia imposed
countersanctions. |
The Company drew up and approved (Directive No. 820r dated 29 December
2014) execution risk management actions related to the Programme for Import
Substitution of Equipment, Technologies, Materials and Systems for 2015–2019.
These actions include:
- Establishment of priorities for implementation of the Company’s investment
projects
- Changes
in the bids documentation and standard delivery contracts in order to
use fixed prices for the calculation of prices for electrical products, and include
clauses about mandatory hedging of currency risks in the delivery period
- Adjustments
in the Company’s technical policy and main technical and
project decisions in order to increase the number and range of domesticallymanufactured
electrical products at the Company’s facilities;
- Transition to the centralised procurement of the main groups of importsubstituted
electrical products
- Long-
term delivery contracts with the Russian producers and those foreign
companies that localise production in the Russian Federation
- Centralisation
of procurement of the main electrical equipment and an increased
share of Russian-made electrical equipment procured for the Company, in
compliance with the applicable legislation
- Encouragement
of innovative development of domestic producers of electrical
equipment
- Communication
with the federal, regional and municipal authorities in order to
ensure support of domestic producers of electrical equipment
|
In Q4 2015, due to Russian sanctions
against Turkey, Russia strengthened the
customs control procedures for Turkish
goods including spare parts for the
manufacture of electrical equipment. This
increases the risk of delayed delivery of
electrical equipment with these spare parts
to the Company’s facilities. |
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Department for the Development
of Technologies for the
Manufacturing of Electrical
Equipment
2014
2015
 |
- Limited or impossible
procurement of electrical
products (caused by legislative
restrictions or ban on import
to Russia either by foreign
countries or by the Russian
Federation); refusal of foreign
producers to co-operate with
the Russian companies;
domestic producers do not
have the required technology,
equipment and competencies
for manufacturing electrical
products that would meet the
present-day requirements)
- Increased prices on electrical
products due to adverse external
factors (Ruble depreciation
against the main currencies;
foreign producers’ discriminatory
policy toward Russian
customers; absence of Russian
analogues of foreign equipment;
or strong dependence of their
manufacturing processes on
imported equipment, inputs and
spare parts)
|
Execution risks related to the Import Substitution
Programme became more relevant in 2015
because external environment further deteriorated,
additional sanctions were imposed on the Russian
Federation by some countries, and Russia imposed
countersanctions. |
The Company drew up and approved (Directive No. 820r dated 29 December
2014) execution risk management actions related to the Programme for Import
Substitution of Equipment, Technologies, Materials and Systems for 2015–2019.
These actions include:
- Establishment of priorities for implementation of the Company’s investment
projects
- Changes
in the bids documentation and standard delivery contracts in order to
use fixed prices for the calculation of prices for electrical products, and include
clauses about mandatory hedging of currency risks in the delivery period
- Adjustments
in the Company’s technical policy and main technical and
project decisions in order to increase the number and range of domesticallymanufactured
electrical products at the Company’s facilities;
- Transition to the centralised procurement of the main groups of importsubstituted
electrical products
- Long-
term delivery contracts with the Russian producers and those foreign
companies that localise production in the Russian Federation
- Centralisation
of procurement of the main electrical equipment and an increased
share of Russian-made electrical equipment procured for the Company, in
compliance with the applicable legislation
- Encouragement
of innovative development of domestic producers of electrical
equipment
- Communication
with the federal, regional and municipal authorities in order to
ensure support of domestic producers of electrical equipment
|
In Q4 2015, due to Russian sanctions
against Turkey, Russia strengthened the
customs control procedures for Turkish
goods including spare parts for the
manufacture of electrical equipment. This
increases the risk of delayed delivery of
electrical equipment with these spare parts
to the Company’s facilities. |
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Operational and Technological
Management Department
2014

2015
 |
This risk is related to high physical
wear and obsolescence of
electricity grid assets, violations of
service conditions and operational
regimes of electric grid equipment,
damages of equipment, wrong
performance of relay protection of
automatic controls and automatic
emergency response system, the
use of inefficient and obsolete
technologies and failure to
implement the repairs programme
in full.
System-wide interruptions in
performance and failures to supply
electricity to customers, either
due do equipment failures or to
natural disasters could eventually
cause significant economic
and reputational losses for the
Company.
Besides, they could affect the
volume of losses in its electric
grids. |
|
Federal Grid Company operates in accordance with the regulation on the Unified
Technical Policy in the Electric Grid Complex. The aim of its implementation is
to enhance the electric grid complex’s reliability and efficiency in the short and
medium term with an appropriate industrial and environmental safety based on
innovative principles of development.
Implementation of the corporate Investment Programme includes projects that aim
to achieve the following goals:
- Reduce the degree of wear of fixed assets
- Renovate electric grid facilities
- Ensure delivery of capacity by power plants and reliability of cross-regional
electric power exchanges
- Upgrade switchgear equipment; upgrade and develop automated process
control systems
- Improve grid manageability and observability
- Clear the routes for overhead transmission lines (OH TLs)
- Improve energy efficiency
- Expand the pool of backup electric power sources, vehicles and special-purpose
machinery for post-accident repairs
- Implement an action plan to prevent an increase of accident rate at high-voltage
lines and substations.
Moreover, the Company implements the following actions toward mitigation of
operational and technological risks:
- Maintains the existing number of repair employees that provide maintenance
and repair of substations and high-voltage lines
- Signs contracts for the servicing of substation equipment with the producers of
electrical equipment
- Educates, oversees and certifies employees who operate process equipment
- Conducts emergency response drills and onsite inspections in the Company’s
branches
- Implements the Property Insurance Coverage Programme
- Oversees operational and technological risks via technical oversight and
maintaining the quality of construction control which is exercised by the
Technical Supervision Centre as Federal Grid’s branch
- Maintains primary equipment at UNEG substations and high voltage lines,
as well as auxiliary equipment at UNEG substations, in a working order in
accordance with the regulatory requirements for maintenance and repair
- Operations of permanent duty teams in the Company’s branches. These teams
are to conduct emergency and recovery work at the grid facilities. Besides,
the Company establishes emergency reserve of equipment in order to ensure
reliable operations of UNEG facilities in cases of disruptions in the electric grids
due either to equipment failures or the aftermath of natural disasters or other emergency situations.
|
|
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Operational and Technological
Management Department
2014

2015
 |
This risk is related to high physical
wear and obsolescence of
electricity grid assets, violations of
service conditions and operational
regimes of electric grid equipment,
damages of equipment, wrong
performance of relay protection of
automatic controls and automatic
emergency response system, the
use of inefficient and obsolete
technologies and failure to
implement the repairs programme
in full.
System-wide interruptions in
performance and failures to supply
electricity to customers, either
due do equipment failures or to
natural disasters could eventually
cause significant economic
and reputational losses for the
Company.
Besides, they could affect the
volume of losses in its electric
grids. |
|
Federal Grid Company operates in accordance with the regulation on the Unified
Technical Policy in the Electric Grid Complex. The aim of its implementation is
to enhance the electric grid complex’s reliability and efficiency in the short and
medium term with an appropriate industrial and environmental safety based on
innovative principles of development.
Implementation of the corporate Investment Programme includes projects that aim
to achieve the following goals:
- Reduce the degree of wear of fixed assets
- Renovate electric grid facilities
- Ensure delivery of capacity by power plants and reliability of cross-regional
electric power exchanges
- Upgrade switchgear equipment; upgrade and develop automated process
control systems
- Improve grid manageability and observability
- Clear the routes for overhead transmission lines (OH TLs)
- Improve energy efficiency
- Expand the pool of backup electric power sources, vehicles and special-purpose
machinery for post-accident repairs
- Implement an action plan to prevent an increase of accident rate at high-voltage
lines and substations.
Moreover, the Company implements the following actions toward mitigation of
operational and technological risks:
- Maintains the existing number of repair employees that provide maintenance
and repair of substations and high-voltage lines
- Signs contracts for the servicing of substation equipment with the producers of
electrical equipment
- Educates, oversees and certifies employees who operate process equipment
- Conducts emergency response drills and onsite inspections in the Company’s
branches
- Implements the Property Insurance Coverage Programme
- Oversees operational and technological risks via technical oversight and
maintaining the quality of construction control which is exercised by the
Technical Supervision Centre as Federal Grid’s branch
- Maintains primary equipment at UNEG substations and high voltage lines,
as well as auxiliary equipment at UNEG substations, in a working order in
accordance with the regulatory requirements for maintenance and repair
- Operations of permanent duty teams in the Company’s branches. These teams
are to conduct emergency and recovery work at the grid facilities. Besides,
the Company establishes emergency reserve of equipment in order to ensure
reliable operations of UNEG facilities in cases of disruptions in the electric grids
due either to equipment failures or the aftermath of natural disasters or other emergency situations.
|
|
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Investment Planning and Reports
Department
2014

2015
 |
Failure to meet the parameters of
the Investment Programme which
is approved by the Ministry of
Energy and taken into account in
tariff decisions results in a decline
of gross revenues when tariffs
are adjusted for the upcoming
period of regulation (in accordance
with the RAB-based regulation
methodology).
Rules of Approval of Investment
Programmes of Electricity Sector
Facilities with State Participation,
and Grid Organisations” (included
in Resolution No. 247 of the
Government of the Russian
Federation (dated 29 March 2014)
became effective. These Rules
may expose the Company to risks
because facilities that are not
included in the regional plans may
be excluded from this Investment
Programme. |
|
The Company has developed and is implementing the following programmes in
order to mitigate the abovementioned risk factors:
- Investment Efficiency Programme (reduction of investment costs)
- Programme for Substitution of Imported Equipment, Technologies, Materials and
Systems for 2015–2019
- Programme for Improving the Efficiency of Technological Connection to Federal
Grid’s Electric Grids and Increasing Transformer Capacity Utilisation.
Besides, the Company implements measures toward fulfilment of an Action Plan
(“road map”) to establish and develop mechanisms of public control over natural
monopolies (in which the power consumers will take part), as approved by Directive
No. 1689-r of the Government of the Russian Federation (dated 19 September 2013).
The Company implements an anti-corruption policy in order to avoid exposures
to fraud in procurement during implementation of the Investment Programme;
actions are taken to assess the good faith and reliability of counterparties. |
|
Risk Disclosing Unit
Risk assessment and changes
in the risk relevance 2014/2015 |
Risk Description/Factors |
Factors that affected risk assessment |
Risk Management Actions |
Risk Materialisation |
Investment Planning and Reports
Department
2014

2015
 |
Failure to meet the parameters of
the Investment Programme which
is approved by the Ministry of
Energy and taken into account in
tariff decisions results in a decline
of gross revenues when tariffs
are adjusted for the upcoming
period of regulation (in accordance
with the RAB-based regulation
methodology).
Rules of Approval of Investment
Programmes of Electricity Sector
Facilities with State Participation,
and Grid Organisations” (included
in Resolution No. 247 of the
Government of the Russian
Federation (dated 29 March 2014)
became effective. These Rules
may expose the Company to risks
because facilities that are not
included in the regional plans may
be excluded from this Investment
Programme. |
|
The Company has developed and is implementing the following programmes in
order to mitigate the abovementioned risk factors:
- Investment Efficiency Programme (reduction of investment costs)
- Programme for Substitution of Imported Equipment, Technologies, Materials and
Systems for 2015–2019
- Programme for Improving the Efficiency of Technological Connection to Federal
Grid’s Electric Grids and Increasing Transformer Capacity Utilisation.
Besides, the Company implements measures toward fulfilment of an Action Plan
(“road map”) to establish and develop mechanisms of public control over natural
monopolies (in which the power consumers will take part), as approved by Directive
No. 1689-r of the Government of the Russian Federation (dated 19 September 2013).
The Company implements an anti-corruption policy in order to avoid exposures
to fraud in procurement during implementation of the Investment Programme;
actions are taken to assess the good faith and reliability of counterparties. |
|